Incident Disclosure 2012

Fire in Firewater Pump Room of SeaRose FPSO

August 8, 2012

Husky Energy, the Operator of the SeaRose FPSO, has reported a fire that occurred in one of the firewater pump rooms on the SeaRose
FPSO
shortly after 5:00 p.m., Tuesday, August 7. The C-NLOPB exercised its regulatory oversight role and monitored the Operator’s response. All personnel were safe and the fire was extinguished. Husky Energy personnel and procedures ensured an appropriate response.

An investigation is underway by the Operator to identify the cause of the fire and the investigation report will be submitted to the C-NLOPB as is required. Husky Energy will provide updates as appropriate.

Media Contact:

C-NLOPB Contact
Sean Kelly
Manager of Public Relations
(709) 778-1418
(709) 689-0713 (cell)
skelly@cnlopb.nl.ca

Husky Energy
Colleen McConnell
Husky Energy Communications
(709) 724-3504


Incident Disclosures 2012

DateUpdate
Oct 16, 2012Scheduled Flight Turnaround
Oct 9, 2012Scheduled Flight Turnaround
Oct 9, 2012Scheduled Flight Turnaround
Oct 4, 2012Scheduled Flight Turnaround
Sep 10, 2012Scheduled Flight Turnaround
Sep 4, 2012Dropped Object – Hibernia
Aug 31, 2012Operations Suspended on Henry Goodrich following Near Miss Incident – Update
Aug 29, 2012Scheduled Flight Turnaround
Aug 27, 2012Operations Suspended on Henry Goodrich following Near Miss Incident
Aug 14, 2012Scheduled Flight Turnaround
Aug 13, 2012False Fire Indication in Helicopter Engine
Aug 9, 2012Scheduled Flight Turnaround
Aug 8, 2012Fire in Firewater Pump Room of SeaRose FPSO
Jul 16, 2012Small Flash Fire on Drill Floor of Henry Goodrich – Update
Jul 11, 2012Small Flash Fire on Drill Floor of Henry Goodrich
May 30, 2012Helicopter on the Deck of Terra Nova FPSO – Update
May 30, 2012Helicopter on the Deck of Terra Nova FPSO – Update
May 29, 2012Helicopter on the Deck of Terra Nova FPSO
May 3, 2012Small Fire in Power Generator C on SeaRose FPSO
Mar 21, 2012Helicopter Input Module Chip Light Illumination
Mar 21, 2012Helicopter Input Module Chip Light Illumination – Update
Jan 11, 2012Scheduled Flight Turnaround