Since successfully plugging the flowline and recovering the failed flowline connector at the South White Rose Extension Drill Centre (SWRX) on March 19, Husky has developed a plan to flush the SWRX flowline. The C-NLOPB has accepted Husky’s plan.
Husky has been monitoring forecasted conditions offshore for an appropriate weather window and has since determined there is a possible window for implementation beginning tomorrow, May 25, 2019.
Aerial surveillance will be on standby, however conditions are required to be suitable for aerial surveillance while operations proceed. There will be Remotely Operated Vehicle (ROV) coverage with Tier 1 spill response equipment available in the field.
Further discussion between the C-NLOPB and Husky will be required prior to resuming production from the SWRX, North Amethyst Drill Centre and the Southern Drill Centre.
Media Contact:
Husky Energy
Colleen McConnell
Husky Energy Communications
(709) 724-3504
Colleen.McConnell@huskyenergy.com
C-NLOPB
Lesley Rideout
Communications Lead
(709) 725-2900
lrideout@cnlopb.ca
Incident Disclosures 2019
Date | Update |
---|
Dec 30, 2019 | Injured Worker on Terra Nova FPSO |
---|
Nov 25, 2019 | Helicopter Return to Base |
---|
Oct 15, 2019 | Near Miss on Terra Nova FPSO |
---|
Oct 3, 2019 | C-NLOPB approves resumption of drilling operations on Transocean Barents |
---|
Sep 26, 2019 | Approval of plans to resume operations at Hibernia and update on follow up to recent offshore incidents |
---|
Sep 9, 2019 | Injured Worker on Transocean Barents |
---|
Aug 21, 2019 | C-NLOPB Update on August 17, 2019 Discharge at the Hibernia Platform |
---|
Aug 18, 2019 | August 17, 2019 Discharge at the Hibernia Platform |
---|
Aug 16, 2019 | C-NLOPB approves re-start of production operations from final two drill centres at White Rose field |
---|
Aug 15, 2019 | C-NLOPB approves resumption of production operations at Hibernia Platform |
---|
Aug 1, 2019 | Update – Hibernia Oil Spill |
---|
Jul 18, 2019 | Hibernia Oil Spill |
---|
Jul 9, 2019 | Incident Bulletin – Near Miss with Potential for Fatality on Terra Nova FPSO |
---|
Jul 5, 2019 | Update – Follow-up to November 2018 Oil Spill at White Rose Field |
---|
Jun 4, 2019 | Near Miss on Hibernia Platform |
---|
May 24, 2019 | Flushing – South White Rose Extension Drill Centre |
---|
Mar 19, 2019 | Update on Plugging of Flowline and Recovery of Flowline Connector at the South White Rose Extension Drill Centre |
---|
Mar 14, 2019 | Near Miss Onboard Terra Nova FPSO |
---|
Mar 13, 2019 | Update on Plugging of Flowline and Recovery of Flowline Connector at the South White Rose Extension Drill Centre |
---|
Jan 30, 2019 | C-NLOPB Issues Approvals to Husky Energy |
---|
Jan 18, 2019 | Update – Status of Spill at White Rose Field |
---|
Jan 11, 2019 | Update – Status of Spill at White Rose Field |
---|
Jan 7, 2019 | Update – Status of Spill at White Rose Field |
---|