Since successfully plugging the flowline and recovering the failed flowline connector at the South White Rose Extension Drill Centre (SWRX) on March 19, Husky has developed a plan to flush the SWRX flowline. The C-NLOPB has accepted Husky’s plan.

Husky has been monitoring forecasted conditions offshore for an appropriate weather window and has since determined there is a possible window for implementation beginning tomorrow, May 25, 2019.

Aerial surveillance will be on standby, however conditions are required to be suitable for aerial surveillance while operations proceed. There will be Remotely Operated Vehicle (ROV) coverage with Tier 1 spill response equipment available in the field.

Further discussion between the C-NLOPB and Husky will be required prior to resuming production from the SWRX, North Amethyst Drill Centre and the Southern Drill Centre.

Media Contact:

Husky Energy
Colleen McConnell
Husky Energy Communications
(709) 724-3504
Colleen.McConnell@huskyenergy.com

C-NLOPB
Lesley Rideout
Communications Lead
(709) 725-2900
lrideout@cnlopb.ca


Incident Disclosures 2019

DateUpdate
June 4, 2019Near Miss on Hibernia Platform
May 24, 2019Flushing – South White Rose Extension Drill Centre
March 19, 2019Update on Plugging of Flowline and Recovery of Flowline Connector at the South White Rose Extension Drill Centre
March 14, 2019Near Miss Onboard Terra Nova FPSO
March 13, 2019Update on Plugging of Flowline and Recovery of Flowline Connector at the South White Rose Extension Drill Centre
January 30, 2019C-NLOPB Issues Approvals to Husky Energy
January 18, 2019Update – Status of Spill at White Rose Field