Part III of the Accord Acts
Pursuant to section 151 of the Atlantic Accord Implementation Acts, the Chief Safety Officer (CSO) and/or the Chief Conservation Officer (CCO) may, on application, permit the use of equipment, methods, measures or standards in lieu of any required by regulations, where those Officers are satisfied that the use of that other equipment and those other methods, measures or standards would provide a level of safety, protection of the environment and conservation equivalent to that provided by compliance with regulations. They may also grant an exemption from any regulatory requirement in respect of equipment, methods, measures or standards, where those Officers are satisfied with the level of safety, protection of the environment and conservation that will be achieved without compliance with that requirement. Pursuant to this section, the application must include information with respect to the consequences to safety, protection of the environment and conservation that might reasonably be anticipated if the permission is granted and be accompanied by technical information sufficient to enable the CSO and/or CCO to make a decision on the application. To document and process such requests from industry, along with requests to clarify the application of specific regulations in specific cases, the Board has developed a “regulatory query process” that is administered by the Operations Department.
Part III.1 of the Accord Acts – Occupational Health and Safety
Pursuant to sections 205.069 and 205.07 of the Atlantic Accord Implementation Acts, the CSO may, on application, permit the use at a workplace or on a passenger craft, for a specified time and subject to specified conditions, of specified equipment, methods, measures, standards or other things, in lieu of any required by regulations made under this Part, if the CSO is satisfied that protection of the health and safety of employees at the workplace or on the passenger craft would not be diminished and the granting of the permission is not otherwise prohibited by regulation. Pursuant to these sections, the application must be in a form acceptable to the CSO, include information with respect to the consequences to health and safety that might reasonably be anticipated if the permission is granted and be accompanied by technical information sufficient to enable the CSO to make a decision on the application. With regards to a passenger craft, the application must also be accompanied by documentation issued by the Minister of Transport indicating that if the permission is granted, it would not contravene any Act or law that applies to the operation of a passenger craft. Applicants should note that while substitutions may be granted, the CSO does not have the authority to grant exemptions from regulations promulgated under this part of the Atlantic Accord Implementation Acts. Any application to the CSO under this part of the Atlantic Accord Implementation Acts will normally be made available to the public for a period of 30 days under the Public Submissions tab.
Regulatory Query Process
If an Operator or installation owner requires clarification on, equivalency for, or exemption from, a regulatory requirement, the applicant must submit a Regulatory Query Form outlining its proposal. For regulations related to the Certificate of Fitness, the proposal must be submitted to the Certifying Authority for their concurrence with the proposal. In addition, for Canadian flagged installations, where a similar requirement is in the Canada Shipping Act and associated regulations, the proposal must also be submitted to Transport Canada Marine Safety for review. The C-NLOPB may also seek advice from Transport Canada Marine Safety on proposals related to marine matters on foreign flagged marine installations or structures.
Following Certifying Authority and/or Transport Canada concurrence with the proposal where required, C-NLOPB staff will review the proposal. If C-NLOPB staff are satisfied that the applicant’s proposal provides for an equivalent level of safety, they will make a recommendation to the CSO and/or the CCO regarding the approval of the proposal.
Decisions are effective from the date of issuance until the earlier of:
a) the date a Regulation referenced is repealed or the date a particular subsection that is the object of a substitution or exemption being granted is amended or replaced, or
b) the date on which the CSO and /or CCO (as applicable) revokes a Decision as a result of i) any enforcement action by the Board related to the Decision or ii) new information or analysis coming to light challenging the assessment upon which the Decision was based, including but not limited to any changes to commitments made by the Applicant in its application.
All applications received in relation to Part III.1 of the Accord Act – Occupational Health and Safety and regulations under that Part are listed below. There is no obligation to publicly post regulatory query applications received in relation to any of the other regulations.
The public is invited to provide comments in relation to an application by submitting them to information@cnlopb.ca. Please include the reference number in all submissions. Any submissions received will be forwarded to the applicant without the name and contact information of the submitter. The applicant will be requested to provide a written response to the CSO. The submissions and applicant’s response will form part of the CSO’s deliberations of the application.
Part III.I Regulatory Substitutions or Exemptions Applications currently under Public Review
As per Part III.1 of the Accord Acts – Occupational Health and Safety (OH&S), any application to the Chief Safety Officer (CSO) for a substitution or exemption in lieu of any required OH&S regulation is normally available to the public for a period of 30 days, unless a shorter timeframe is acknowledged by the Workplace Committee and CSO.As we continue to respond to the current global concern of COVID-19, we have determined that it may be appropriate to shorten the public review period, in consultation with offshore operator workplace committees, for particular submissions.
Reference Number | Installation | Applicant | Application | Date Posted | Deadline for Public Submission |
---|
| | | | | |
Substitutions or Exemptions 2024
All reports pertaining to 2024 are listed below.
Notice from the Chief Safety Officer, effective January 1, 2021:
Governments are further extending the expiry date of the transitional regulations that came into force on December 31, 2014 associated with Part III.1 of the Canada – Newfoundland and Labrador Atlantic Accord Implementation Act (AAIA). Accordingly, the Chief Safety Officer advises that the Decision Report for any applicable Regulatory Query that was previously approved and remained in effect on December 31, 2020 is changed to read as follows:
“This exemption or substitution will remain effective until the Canada–Newfoundland and Labrador Marine Installations and Structures Occupational Health and Safety Transitional Regulations are repealed or any representations made in the application for exemption or substitution have changed, whichever is earlier.”
Operators have been advised that it is not necessary to resubmit a new application for any of those Regulatory Queries and that related correspondence has been placed on the associated files.
Hebron Platform
Applicant | Application | Date of Decision |
---|
ExxonMobil Canada Properties | Shale Shaker Cabling | |
ExxonMobil Canada Properties | MPD RCD Sensor Cable | |
ExxonMobil Canada Properties | MPD RCD Sensor Cable | |
ExxonMobil Canada Properties | PSV Recertification Frequency | |
West White Rose Platform
Applicant | Application | Date of Decision |
---|
Cenovus Energy | Use of Phenolic Grating | |
Cenovus Energy | Use of FRP Grating on Equipment Skids | |
MV-Stena DrillMAX
Applicant | Application | Date of Decision |
---|
Stena Drilling Ltd. | Quality Assurance | |
Stena Drilling Ltd | Secondary Structures | |
Stena Drilling Ltd. | Hazardous Area | |
Stena Drilling Ltd. | Helicopter Deck | |
Stena Drilling Ltd. | Self-Closing Gastight Doors | |
Stena Drilling Ltd. | Airlock Arrangements | |
Stena Drilling Ltd. | Emergency Source of Electrical Power | |
Stena Drilling Ltd. | Emergency Power Location | |
Stena Drilling Ltd. | Rescue Baskets | |
Stena Drilling Ltd. | Mechanical Equipment | |
Stena Drilling Ltd. | Offshore Cranes | |
Stena Drilling Ltd. | Construction of Offshore Structures | |
Stena Drilling Ltd. | Engine Shutdowns | |
Stena Drilling Ltd. | Electrical Equipment and Wiring | |
Stena Drilling Ltd. | Self-Closing Gaslight Doors | |
Stena Drilling Ltd. | Alarm Panels & Signals | |
Stena Drilling Ltd. | Non-Combustible Materials | |
Stena Drilling Ltd. | Steel Structures | |
Stena Drilling Ltd. | Windows and Side Scuttles | |
Stena Drilling Ltd. | Hot Work | |
Stena Drilling Ltd. | Accommodation Sprinkler System | |
Stena Drilling Ltd. | Escape Routes | |
Stena Drilling Ltd. | Navigational Lights | |
Stena Drilling Ltd. | Fire Hydrants and Hoses | |
Stena Drilling Ltd. | Fixed CO2 System | |
Stena Drilling Ltd. | Comprehensive Inspection | |
Stena Drilling Ltd. | Fire and Gas Detection Systems | |
Stena Drilling Ltd. | Deluge System | |
Stena Drilling Ltd. | Carbon Dioxide (CO2) Fire Extinguisher Capacity | |
Stena Drilling Ltd. | Fixed Water Spray System | |
Stena Drilling Ltd. | Passive Fire Protection | |
Stena Drilling Ltd. | Fixed Fire System Alarms | |
Stena Drilling Ltd. | Fixed Foam System | |
Hibernia Platform
Applicant | Application | Date of Decision |
---|
Hibernia Management and Development Company Inc. | Structural Design Codes for Topside ALE Fatigue Analysis | |
Terra Nova FPSO
Applicant | Application | Date of Decision |
---|
Suncor Energy Inc. | Manual Flare Ignition Arrangement | |
Suncor Energy Inc. | POB Upmanning to 160 | |
FFPV Stornes
Applicant | Application | Date of Decision |
---|
Van Oord | Conveyor Boom Access Ladder | |
Van Oord | Fall Protection EN Markings | |
DSV-Deep Explorer
Applicant | Application | Date of Decision |
---|
TechnipFMC | Fall Protection Equipment | |
TechnipFMC | LDC Dive Supervisors | |
TechnipFMC | Elevating Devices | |
Substitutions or Exemptions 2023
All reports pertaining to 2023 are listed below.
Notice from the Chief Safety Officer, effective January 1, 2021:
Governments are further extending the expiry date of the transitional regulations that came into force on December 31, 2014 associated with Part III.1 of the Canada – Newfoundland and Labrador Atlantic Accord Implementation Act (AAIA). Accordingly, the Chief Safety Officer advises that the Decision Report for any applicable Regulatory Query that was previously approved and remained in effect on December 31, 2020 is changed to read as follows:
“This exemption or substitution will remain effective until the Canada–Newfoundland and Labrador Marine Installations and Structures Occupational Health and Safety Transitional Regulations are repealed or any representations made in the application for exemption or substitution have changed, whichever is earlier.”
Operators have been advised that it is not necessary to resubmit a new application for any of those Regulatory Queries and that related correspondence has been placed on the associated files.
M/V Stena IceMAX
Applicant | Application | Date of Decision |
---|
Stena Drilling Ltd. | Electrical Equipment in Hazardous Area | |
Stena Drilling Ltd. | Hot Work | |
SeaRose FPSO
Applicant | Application | Date of Decision |
---|
Cenovus Energy | Deadweight Surveys | |
Cenovus Energy | Increased POB Post Shutdown and Prior to Start Up | |
Terra Nova FPSO
Applicant | Application | Date of Decision |
---|
Suncor Energy Inc. | SCSSV and USV Shutdown on Separate ESD Levels | |
Suncor Energy Inc. | QCDC Rooms ESV(s) Removal during Reconnect Operations | |
Suncor Energy Inc. | Increase of POB to 160 for Voyage | |
Hebron Platform
Applicant | Application | Date of Decision |
---|
ExxonMobil Canada Properties | Hebron Knuckle Boom Crane – Drag Chain Cables | |
ExxonMobil Canada Properties | Isolation Tags | |
ExxonMobil Canada Properties | Flare Boom Inspection Program | |
ExxonMobil Canada Properties | Hebron SCE Electrical Maintenance | |
Hercules
Applicant | Application | Date of Decision |
---|
Odfjell Drilling | Mooring | |
Odfjell Drilling | Portable Fire Extinguisher | |
Hibernia Platform
Applicant | Application | Date of Decision |
---|
Hibernia Management Development Company | Piping Isolation for M30 Seal Pot Pit | |
Hibernia Management Development Company | Isolation Tags | |
Hibernia Management Development Company | CSE – Intermodular Zones | |
Substitutions or Exemptions 2022
All reports pertaining to 2022 are listed below.
Notice from the Chief Safety Officer, effective January 1, 2021:
Governments are further extending the expiry date of the transitional regulations that came into force on December 31, 2014 associated with Part III.1 of the Canada – Newfoundland and Labrador Atlantic Accord Implementation Act (AAIA). Accordingly, the Chief Safety Officer advises that the Decision Report for any applicable Regulatory Query that was previously approved and remained in effect on December 31, 2020 is changed to read as follows:
“This exemption or substitution will remain effective until the Canada–Newfoundland and Labrador Marine Installations and Structures Occupational Health and Safety Transitional Regulations are repealed or any representations made in the application for exemption or substitution have changed, whichever is earlier.”
Operators have been advised that it is not necessary to resubmit a new application for any of those Regulatory Queries and that related correspondence has been placed on the associated files.
GBS-Hibernia Platform
Applicant | Application | Date of Decision |
---|
Hibernia Management Development Company | Foghorn Operations | |
Hibernia Management Development Company | Portable Fire Extinguisher Spares | |
Hibernia Management Development Company | Hot Work Within Hibernia M33 Modules | |
Hibernia Management Development Company | Flare Boom Ladder Underside Angle | |
Hibernia Management Development Company | Turnaround Lifeboat Arrangement | |
Hibernia Management Development Company | Piping Isolation for nHODT tank F-5101 | |
GBS-Hebron Platform
Applicant | Application | Date of Decision |
---|
ExxonMobil Canada Properties | Hebron Foghorn Operations | |
ExxonMobil Canada Properties | Pressure Vessel Risk Based Inspection Program | |
ExxonMobil Canada Properties | Flare Boom Ladder Underside Angle | |
ExxonMobil Canada Properties | Alarm Tones | |
ExxonMobil Canada Properties | Piping Isolation in Void Spaces | |
MODU- West Hercules
Applicant | Application | Date of Decision |
---|
Seadrill Newfoundland | Cranes | |
Seadrill Newfoundland | Water Deluge-Monitor System | |
Seadrill Newfoundland | Sprinkler System in Accommodation Area | |
Seadrill Newfoundland | Helicopter Deck | |
Seadrill Newfoundland | Hot Work Operations | |
Seadrill Canada Ltd. | Emergency Electrical Power | |
Seadrill Canada Ltd. | Electrical and Hazardous Area | |
DSV- Seven Falcon
Applicant | Application | Date of Decision |
---|
Subsea 7 Canada Inc. | Fall Protection Systems | |
Subsea 7 Canada Inc. | Loose Lifting Gear | |
Subsea 7 Canada Inc. | Elevating Devices | |
Subsea 7 Canada Inc. | Fixed Ladders | |
SeaRose FPSO
Applicant | Application | Date of Decision |
---|
Cenovus | Closure of SCSSV Following Christmas Tree Safety Valve | |
Cenovus | Propulsion System Comprehensive Inspection | |
Stena Forth
Applicant | Application | Date of Decision |
---|
Stena Drilling | Electrical Equipment | |
Terra Nova FPSO
Applicant | Application | Date of Decision |
---|
Suncor Energy Inc. | Fixed Ladders-Support Intervals | |
Suncor Energy Inc. | Insolation for Tank Entry | |
Suncor Energy Inc. | Breaking Integrity Inside QCDC Room Above Emergency Safety Valve’s (ESV) and J-Plates | |
West White Rose Platform
Applicant | Application | Date of Decision |
---|
Cenovus Energy | Alternate Electrical Codes Certification | |
Substitutions or Exemptions 2021
All reports pertaining to 2021 are listed below.
Notice from the Chief Safety Officer, effective January 1, 2021:
Governments are further extending the expiry date of the transitional regulations that came into force on December 31, 2014 associated with Part III.1 of the Canada – Newfoundland and Labrador Atlantic Accord Implementation Act (AAIA). Accordingly, the Chief Safety Officer advises that the Decision Report for any applicable Regulatory Query that was previously approved and remained in effect on December 31, 2020 is changed to read as follows:
“This exemption or substitution will remain effective until the Canada–Newfoundland and Labrador Marine Installations and Structures Occupational Health and Safety Transitional Regulations are repealed or any representations made in the application for exemption or substitution have changed, whichever is earlier.”
Operators have been advised that it is not necessary to resubmit a new application for any of those Regulatory Queries and that related correspondence has been placed on the associated files.
SeaRose FPSO
Applicant | Application | Date of Decision |
---|
Husky Energy | Use of Lifelines in Confined Spaces | |
GBS-Hebron Platform
Applicant | Application | Date of Decision |
---|
ExxonMobil Canada Ltd. | Diesel Engine Maintenance Strategy In Lieu of 5 Year Comprehensive Inspection | |
MV Stena Forth
Applicant | Application | Date of Decision |
---|
Stena Drilling | Quality Assurance | |
Stena Drilling | Secondary Structure and Fittings | |
Stena Drilling | Installation Maintenance and Operation of Internal Combustion Engines | |
Stena Drilling | Rescue Baskets | |
Stena Drilling | Emergency Source of Electrical Power Location | |
Stena Drilling | Escape Route | |
Stena Drilling | General Electric Standards | |
Stena Drilling | Navigation Equipment | |
Stena Drilling | Diesel Engine Equipped with Manual Shut off Device | |
Stena Drilling | Construction and Installation of Platforms | |
Stena Drilling | Design of Installations and Platforms | |
Stena Drilling | Fire Detection System | |
Stena Drilling | Emergency Electrical Power | |
Stena Drilling | Fire Hydrants and Hoses | |
Stena Drilling | Piping Systems | |
Stena Drilling | Fire Pump Alarms | |
Stena Drilling | Airlocks in Accommodation | |
Stena Drilling | Comprehensive Inspection Thrusters | |
Stena Drilling | Stability – Angle of Heel | |
Stena Drilling | Deadlights and Side Scuttles | |
Stena Drilling | Offshore Cranes | |
Stena Drilling | Self-Closing Gastight Doors | |
Stena Drilling | Hazardous Area Classification | |
Stena Drilling | Design and Fatigue Analysis | |
Stena Drilling | Steel Structures Standards | |
Stena Drilling | Corrosion Protection | |
Stena Drilling | Accommodation Sprinkler System | |
Stena Drilling | CO2 Fixed Fie Extinguishing System | |
Stena Drilling | Lifeboat Arrangement | |
Stena Drilling | Self-Closing Gastight Doors between Class 1 Div. 1 Spaces | |
Stena Drilling | Fixed Water Spray System | |
Stena Drilling | Fixed Fire Extinguishing System Visual and Audible Alarms | |
Stena Drilling | Alarm Panels and Signals | |
Stena Drilling | Non-Combustible Material Piping | |
Stena Drilling | Passive Fire Protection | |
Stena Drilling | Helicopter Deck | |
Stena Drilling | Comprehensive Inspections – Main Engines | |
Stena Drilling | Deluge Systems | |
Stena Drilling | Pressure Water and Foam Fire Extinguishing System | |
Stena Drilling | Hot Work | |
West White Rose Platform
Applicant | Application | Date of Decision |
---|
Husky Energy | SCSSV and ASV Shutdown Logic | |
Substitutions or Exemptions 2020
All reports pertaining to 2020 are listed below.
Notice from the Chief Safety Officer, effective January 1, 2021:
Governments are further extending the expiry date of the transitional regulations that came into force on December 31, 2014 associated with Part III.1 of the Canada – Newfoundland and Labrador Atlantic Accord Implementation Act (AAIA). Accordingly, the Chief Safety Officer advises that the Decision Report for any applicable Regulatory Query that was previously approved and remained in effect on December 31, 2020 is changed to read as follows:
“This exemption or substitution will remain effective until the Canada–Newfoundland and Labrador Marine Installations and Structures Occupational Health and Safety Transitional Regulations are repealed or any representations made in the application for exemption or substitution have changed, whichever is earlier.”
Operators have been advised that it is not necessary to resubmit a new application for any of those Regulatory Queries and that related correspondence has been placed on the associated files.
CGS-West White Rose Platform
Applicant | Application | Date of Decision |
---|
Husky Energy | Cellar Deck Fire Rating Adjacent to CGS | |
Husky Energy | Fire Rating of the East Barrier Wall | |
Husky Energy | Pedestal Crane Electrical Design and Fabrication | |
DSV-Deep Explorer
Applicant | Application | Date of Decision |
---|
Technip FMC | Quality Assurance | |
Technip FMC | Navigational Equipment | |
Technip FMC | Sprinkler System in the Accommodations Area | |
Technip FMC | Mechanical Equipment | |
Technip FMC | Automatic Fire Detection Systems | |
Technip FMC | Lifesaving Equipment | |
Technip FMC | Design Codes and Standards | |
Technip FMC | Mechanical Equipment Fire Hydrant Systems | |
Technip FMC | Piping Systems Design Codes and Standards | |
Technip FMC | General Electrical Standards | |
Technip FMC | Ventilation of Hazardous Areas | |
Technip FMC | Alarms Panels and Signals | |
Technip FMC | Escape Routes | |
Technip FMC | Helideck | |
Technip FMC | Firefighting Equipment | |
Technip FMC | Fire Extinguishing Systems in Machinery and Flammable Liquid Storage Spaces | |
Technip FMC | Fire Extinguishers | |
Technip FMC | Bilge and Ballast Systems | |
Technip FMC | Stability and Water Tight Integrity | |
Technip FMC | Emergency Electrical Power | |
GBS-Hibernia Platform
Applicant | Application | Date of Decision |
---|
Hibernia Management Development Company | Certification of Crane Electrical Equipment | |
Hibernia Management and Development Company | 5-year Comprehensive Inspection One Time Deferral – Flare Boom Inspection | |
Hebron
Applicant | Application | Date of Decision |
---|
ExxonMobil Canada | Hebron Deluge Integrity Testing | |
MV-Stena IceMAX
Applicant | Application | Date of Decision |
---|
Stena Drilling Limited | Fire Pump Alarms | |
Stena Drilling Limited | Helideck | |
Stena Drilling Limited | Portable Fire Extinguishers | |
Stena Drilling Limited | Rescue Basket | |
Stena Drilling Limited | Navigation Lights | |
Stena Drilling Limited | Accommodation Sprinkler System | |
Stena Drilling Limited | Mechanical Equipment | |
Stena Drilling Limited | Engine Exhaust Temperature Shutdown | |
Stena Drilling Limited | Emergency Escape Routes | |
Stena Drilling Limited | Quality Assurance Program | |
Stena Drilling Limited | Classification of Hazardous Areas | |
Stena Drilling | Location of Emergency Power Sources | |
Stena Drilling | Structural Steel | |
Stena Drilling | Shakerhouse Airlock | |
Stena Drilling | Hazardous Areas | |
Stena Drilling Ltd. | CSA Design and Environmental Loads | |
Stena Drilling Ltd. | Thruster Comprehensive Inspection | |
Stena Drilling Ltd. | Design and Fatigue Analyses | |
Stena Drilling Limited | Design Loads | |
Stena Drilling Limited | Electrical Equipment | |
Stena Drilling Limited | Structural Corrosion Protection | |
Stena Drilling Limited | Fabrication and Construction Standards | |
Stena Drilling Limited | Offshore Cranes | |
Stena Drilling Limited | Deadlight Covers | |
Stena Drilling Limited | Engine Inspections | |
Stena Drilling Limited | Piping Design and Installation | |
Stena Drilling Limited | Non-Combustible Piping | |
Stena Drilling Limited | Water Deluge System | |
Stena Drilling inc. | Electrical Equipment in Hazardous Areas | |
Stena Drilling inc. | Fire Detection System | |
Stena Drilling | F&G System Activation and NFPA | |
Stena Drilling | Fire Hoses | |
Stena Drilling Ltd. | Fixed CO2 Fire Extinguishing System | |
Stena Drilling Ltd. | Fixed Water Spray Fire Extinguishing System | |
Stena Drilling Ltd. | Fixed Fire Fighting Discharge Alarms | |
Stena Drilling Ltd. | Emergency Electrical Power | |
Stena Drilling Ltd. | Accommodation Bulkheads | |
Stena Drilling | Fixed Foam Fire Extinguishing System | |
Transocean Barents
Applicant | Application | Date of Decision |
---|
Transocean Offshore (Canada) Services Ltd. | Deadweight Survey | |
Transocean Offshore (Canada) Services Ltd | Navigation Equipment | |
Substitutions or Exemptions 2019
All reports pertaining to 2019 are listed below.
Hebron
Applicant | Application | Date of Decision |
---|
ExxonMobil Canada Ltd., as managing partner of ExxonMobil Canada Properties | Domestic Potable Water System Piping | |
Hibernia
Applicant | Application | Date of Decision |
---|
Hibernia Management and Development Company | Hot Work/Non-Flame Hot Work During Underdeck Scope | |
SeaRose FPSO
Applicant | Application | Date of Decision |
---|
Husky Energy | Helideck Fire Monitor Height | |
Terra Nova FPSO
Applicant | Application | Date of Decision |
---|
Suncor Energy | Limited Use of Combustible Materials in Public Spaces | |
Suncor Energy | MPG Hot Gas Path and Major Inspections – Manufacturer’s Maintenance Schedule | |
West White Rose Project
Applicant | Application | Date of Decision |
---|
Husky Energy | Water Mist Suppression Systems | |
Husky Energy | Use of Plastic Safety Gates | |
Husky Energy | Mud Tank Fire Protection | |
Husky Energy | Lifeboat Arrangements | |
Husky Energy | Analytical Approach to Passive Fire Protection (PFP) | |
Husky Energy | Sprinkler Protection of Flammable Storage Locker | |
Husky Energy | Aviation Fuel Skid Electrical | |
Husky Energy | VHF Hand Portable Radios Electrical Certification | |
Husky Energy | HP Mud Pump Main Motors Certification | |
Husky Energy | Cold Impact-Bend Testing Flare Ignition Cable | |
Substitutions or Exemptions 2018
All reports pertaining to 2018 are listed below.
Hebron
Applicant | Application | Date of Decision |
---|
ExxonMobil Canada Properties | Surface-Controlled Sub-Surface Safety Valve (SCSSV) Shutdown | |
ExxonMobil Canada Properties | Diverter Retirement | |
ExxonMobil Canada Ltd., as managing partner of ExxonMobil Canada Properties | Hebron Contingent Hot Work During Production Operations – Southwest Pedestal Crane Heel Pin Removal | |
ExxonMobil Canada Ltd., as managing partner of ExxonMobil Canada Properties | Hebron Hot Work During Production Operations | |
Hibernia Management and Development Company
Applicant | Application | Date of Decision |
---|
Hibernia Management Development Company | Hibernia Safety Critical Equipment – 5-year Comprehensive Inspection – Switchboard Maintenance | |
SeaRose FPSO
Applicant | Application | Date of Decision |
---|
Husky Energy | Comprehensive Inspection of Critical Production Equipment | |
Terra Nova FPSO
Applicant | Application | Date of Decision |
---|
Suncor Energy | Main Power Generator Starting Diesel Engine Shutdowns | |
Suncor Energy | Replacement of Deluge Klack Valves with Actuated Butterfly Valves | |
West White Rose Platform
Applicant | Application | Date of Decision |
---|
Husky Energy | Certifying Authority as an Alternate Electrical Certification Organization | |
Husky Energy | Spare Fire Extinguishers | |
Husky Energy | Removal of Integrity Instrumentation and Monitoring System (IIMS) | |
Husky Energy | Alarm Tone Harmonization | |
Husky Energy | Definition of Machinery Space for Passive Fire Protection (PFP) Requirements | |
Husky Energy | Fog Horn | |
Husky Energy | Hose Reels | |
Husky Energy | Rescue Craft | |
Husky Energy | Sprinkler Water Supply | |
Substitutions or Exemptions 2017
All reports pertaining to 2017 are listed below.
Hebron
Applicant | Application | Date of Decision |
---|
ExxonMobil Canada Ltd., as managing partner of ExxonMobil Canada Properties | Use of Intrepid Industries Safety Gates on Hebron | |
ExxonMobil Canada Ltd., as managing partner of ExxonMobil Canada Properties | Use of Temporary Wood Products and Non-Load Bearing FRP Grating | |
ExxonMobil Canada Ltd., as managing partner of ExxonMobil Canada Properties | Use of IECEx and ATEX for Hazardous Area Rated Equipment | |
ExxonMobil Canada East | Fibre Optic Cable Splice | |
ExxonMobil Canada Ltd. | Clarification of Hot Work Regulations Pertaining to Welding | |
ExxonMobil Canada | Use of Firewater for Air Compressor Skid Cooling During Black Start | |
ExxonMobil Canada Ltd., as managing partner of ExxonMobil Canada Properties | Lloyds Register Nomination as AIA for Pressure Vessels | |
ExxonMobil Canada Properties | Coiled Tubing Unit Operations | |
Hibernia Management and Development Company
Applicant | Application | Date of Decision |
---|
Hibernia Management and Development Company | Use of Combilift in Hazardous Rated Areas | |
Hibernia Management and Development Company | Safety Critical Equipment 5-Year Comprehensive Inspection – IOP-MPO In-Line Inspections | |
Hibernia Management and Development Company | Use of IECEx and ATEX for Hazardous Area Rated Equipment | |
MODU Transocean Barents
Applicant | Application | Date of Decision |
---|
Transocean Offshore (Canada) Services Ltd. | Mooring Analysis | |
Transocean Offshore (Canada) Services Ltd. | Ventilation of Hazardous Areas | |
Transocean Offshore (Canada) Services Ltd. | Thrusters | |
Transocean Offshore (Canada) Services Ltd. | Automatic Fire Detection Systems | |
Transocean Offshore (Canada) Services Ltd. | Fire Extinguishers | |
Transocean Offshore (Canada) Services Ltd. | Six Person Rescue Craft | |
Transocean Offshore (Canada) Services Ltd. | Escape Routes | |
Transocean Canada Drilling Services Ltd. | General Requirements for Fire Pump and Water Mains | |
Transocean Canada Drilling Services Ltd. | Emergency Shutdown System | |
Transocean Offshore (Canada) Services Ltd. | Emergency Power | |
Transocean Offshore (Canada) Services Ltd. | Installation Stability Calculations | |
Transocean Canada Drilling Services Ltd. | General Design, Construction and Installation Standards – Environmental Criteria and Loads | |
Transocean Canada Drilling Services Ltd. | Sprinkler System in Accommodations Area | |
Transocean Canada Drilling Services Ltd. | Watertight Integrity of Floating Platforms | |
Transocean Canada Drilling Services Ltd. | Fire Extinguishing Systems in Machinery and Flammable Liquid Storage Spaces | |
Transocean Offshore (Canada) Services Ltd. | Life Saving Equipment for Installations | |
Transocean Offshore (Canada) Services Ltd. | Fire Hoses and Nozzles | |
Transocean Offshore (Canada) Services Ltd. | Helicopter Deck | |
Transocean Offshore (Canada) Services Ltd. | Fire Extinguishing Systems | |
Transocean Canada Drilling Services Ltd. | General Design, Construction, and Installation Standards | |
Transocean Canada Drilling Services Ltd. | Lifesaving Equipment for Installations | |
Transocean Canada Drilling Services Ltd. | Water Deluge and Water Monitor Systems in Areas with Petroleum | |
Transocean Offshore (Canada) Services Ltd. | Quality Assurance | |
Transocean Canada Drilling Services Ltd. | Navigation Equipment | |
Transocean Canada Drilling Services Ltd. | General Electrical Standards | |
Transocean Canada Drilling Services Ltd. | Mechanical Equipment | |
Transocean Canada Drilling Services Ltd. | Passive Fire and Blast Protection | |
Transocean Canada Drilling Services Ltd. | General Requirements for Fire Pump Systems and Water Main | |
Transocean Canada Drilling Services Ltd. | Mechanical Equipment – Shut-off Devices | |
Transocean Canada Drilling Services Ltd. | Classification of Hazardous Areas | |
Transocean Canada Drilling Serivcess Ltd. | Piping System Design | |
Transocean Offshore (Canada) Services Ltd. | Hotwork | |
SeaRose FPSO
Applicant | Application | Date of Decision |
---|
Husky Energy | Use of ATEX and IEC Approved Electrical Equipment | |
Substitutions or Exemptions 2016
All reports pertaining to 2016 are listed below.
Hebron
Applicant | Application | Date of Decision |
---|
ExxonMobil Canada Ltd. | Clarification of Firefighting Equipment in Topsides Electrical Spaces | |
ExxonMobil Canada Ltd. | Deviation from Cold Bend/Cold Impact Testing Requirements | |
ExxonMobil Canada Ltd. | Alternatives to Cold Bend/Cold Impact Testing of Cables | |
Hibernia Management and Development Company
Applicant | Application | Date of Decision |
---|
Hibernia Management and Development Company | Hot Work During Rig Upgrade Period- PHM and Fingerboard Repairs | |
Hibernia Management and Development Company | Hot Work/Non-Flame Hot Work During Underdeck Scope | |
Hibernia Management and Development Company | Hot Work/Non-Flame Hot Work During Production | |
Husky Oil Operations
Applicant | Application | Date of Decision |
---|
Husky Oil Operations | Thermal Radiation Limit | |
Husky Oil Operations | Helideck Standard | |
SeaRose FPSO
Applicant | Application | Date of Decision |
---|
Husky Energy | Use of Alternate Pressure Safety Valve (PSV) for Foam Tank Skids | |
West Hercules
Applicant | Application | Date of Decision |
---|
Seadrill Canada Limited | Emergency Electrical Power and Emergency Shutdown System | |
Substitutions or Exemptions 2015
All reports pertaining to 2015 are listed below.
Hebron
Applicant | Application | Date of Decision |
---|
ExxonMobil Canada Ltd. | Proposal for Use of Mineral Insulated (MI) Metal Sheathed Cables on the Flare Boom for the Connection to the Frost Heaters and Thermocouples at the Flare Tip | |
ExxonMobil Canada Ltd. | Hose Reel on UPM Cellar Deck | |
Hibernia
Applicant | Application | Date of Decision |
---|
Hibernia Management and Development Company | Emergency Shutdown System | |
West Hercules
Applicant | Application | Date of Decision |
---|
Seadrill Canada Limited | Usage of Arctic Offshore Structures | |
Seadrill Canada Limited | Fixed Fire Extinguishing Systems | |
Seadrill Canada Limited | Thruster Maintenance | |
Substitutions or Exemptions 2014
All reports pertaining to 2014 are listed below.
Hebron
Date | Applicant |
---|
| ExxonMobil Canada Ltd. |
| ExxonMobil Canada Ltd. |
| ExxonMobil Canada Ltd. |
| ExxonMobil Canada Ltd. |
| ExxonMobil Canada Ltd. |
| ExxonMobil Canada Ltd. |
| ExxonMobil Canada Ltd. |
Hibernia GBS
Husky Wellhead Platform
Date | Applicant |
---|
| Husky Oil Operations Ltd. |
| Husky Oil Operations Ltd. |
| Husky Oil Operations Ltd. |
| Husky Oil Operations Ltd. |
| Husky Oil Operations Ltd. |
Terra Nova FPSO
Date | Applicant |
---|
| Suncor Energy Inc. |
| Suncor Energy Inc. |
| Suncor Energy Inc. |
| Suncor Energy Inc. |
West Hercules
Date | Applicant |
---|
| Seadrill Canada Limited |
| Seadrill Canada Limited |
| Seadrill Canada Limited |
| Seadrill Canada Limited |
| Seadrill Canada Limited |
| Seadrill Canada Limited |
| Seadrill Canada Limited |
| Seadrill Canada Limited |
| Seadrill Canada Limited |
| Seadrill Canada Limited |
| Seadrill Canada Limited |
| Seadrill Canada Limited |
| Seadrill Canada Limited |
| Seadrill Canada Limited |
| Seadrill Canada Limited |
| Seadrill Canada Limited |
| Seadrill Canada Limited |
| Seadrill Canada Limited |
Substitutions or Exemptions 2013
All reports pertaining to 2013 are listed below.
Hebron
Date | Applicant |
---|
| ExxonMobil Canada Ltd. |
| ExxonMobil Canada Ltd. |
| ExxonMobil Canada Ltd. |
| ExxonMobil Canada Ltd. |
| ExxonMobil Canada Ltd. |
| ExxonMobil Canada Ltd. |
| ExxonMobil Canada Ltd. |
| ExxonMobil Canada Ltd. |
| ExxonMobil Canada Ltd. |
| ExxonMobil Canada Ltd. |
| ExxonMobil Canada Ltd. |
| ExxonMobil Canada Ltd. |
| ExxonMobil Canada Ltd. |
Husky Wellhead Platform
Date | Applicant |
---|
| Husky Oil Operations Ltd. |
| Husky Oil Operations Ltd. |
| Husky Oil Operations Ltd. |
| Husky Oil Operations Ltd. |
| Husky Oil Operations Ltd. |
SeaRose FPSO
Date | Applicant |
---|
| Husky Oil Operations Ltd. |
Terra Nova FPSO
Date | Applicant |
---|
| Suncor Energy Inc. |
| Suncor Energy Inc. |
| Suncor Energy Inc. |
| Suncor Energy Inc. |
| Suncor Energy Inc. |
Substitutions or Exemptions 2012
All reports pertaining to 2012 are listed below.
Hebron
Date | Applicant |
---|
| ExxonMobil Canada Ltd. |
| ExxonMobil Canada Ltd. |
| ExxonMobil Canada Ltd. |
| ExxonMobil Canada Ltd. |
| ExxonMobil Canada Ltd. |
| ExxonMobil Canada Ltd. |
| ExxonMobil Canada Ltd. |
| ExxonMobil Canada Ltd. |
| ExxonMobil Canada Ltd. |
Hibernia GBS
Date | Applicant |
---|
| HMDC |
| HMDC |
| HMDC |
| HMDC |
SeaRose FPSO
Date | Applicant |
---|
| Husky Oil Operations Ltd. |
Terra Nova FPSO
Date | Applicant |
---|
| Suncor Energy Inc. |
| Suncor Energy Inc. |
| Suncor Energy Inc. |
| Suncor Energy Inc. |
| Suncor Energy Inc. |
Substitutions or Exemptions 2011
All reports pertaining to 2011 are listed below.
Hebron
Date | Applicant |
---|
| ExxonMobil Canada Ltd. |
| ExxonMobil Canada Ltd. |
Hibernia GBS
Date | Applicant |
---|
| HMDC |
| HMDC |
| HMDC |
SeaRose FPSO
Date | Applicant |
---|
| Husky Oil Operations Ltd. |
| Husky Oil Operations Ltd. |
Terra Nova FPSO
Date | Applicant |
---|
| Suncor Energy Inc. |
Substitutions or Exemptions 2010
All reports pertaining to 2010 are listed below.
Hebron
Date | Applicant |
---|
| ExxonMobil Canada Ltd. |
Hibernia GBS
SeaRose FPSO
Date | Applicant |
---|
| Husky Oil Operations Ltd. |
| Husky Oil Operations Ltd. |
| Husky Oil Operations Ltd. |
Terra Nova FPSO
Date | Applicant |
---|
| Suncor Energy Inc. |
| Suncor Energy Inc. |